Traffic Alerts and Construction Updates.jpg
Epoxy deck treaments on the stretch of road from the Rt. 15 interchange to the Fairfield Rd. interchange will result in single lane conditions from Friday, Sept. 13 at 8 p.m. to Monday, Sept. 16 at 6 a.m., according to PennDOT.
 
Single lane conditions should also be expected on I-180 near the pedestrian underpass, as the contractor will be installing a new roof on the pedestrian overpass. This work will take place over the next few weekends. 
 
Sunday night, milling and paving operations will resume on the ramps associated with the Faxon Interchange, Basin Street, and Hepburn Street with short-term single lane conditions. The work will be completed during weekday nights between 8 p.m until 6 a.m.